Wednesday 25 March 2015

Hong Kong International Airport Project


It aimed to be boasting of largest passenger
terminal in the world, world's busiest
airport by cargo traffic, and also one of
the busiest airports by passenger traffic in
the world. It was about to be the most
expensive airport project costing about US
$20 billion. And it was to be completed in
a record period of 6-7 years. The airport
was itself just a small fraction of the
whole project . Why I say so, lets see..
Major challenges it faced:
1. Site Selection - The search for land
began. But as no land was available, a
large artificial island was created
offshore by merging small islands.
Mechanism - The mountainous islands
had to be levelled which resulted in
removing 200 million tons of rocks by
giant earth movers. The excavated
rubble was used to fill the sea gap
between small islands. Before filling
the sea gaps by rubble, soft mud
(approx. 40 ft) had to be removed from
the sea (to ensure a solid foundation).
Hence the largest fleet of under water
dredgers arrived at the site. This all
proved to be the biggest land moving
exercises ever i.e. 600 million tons of
material was removed which is
enough to fill ancient Roman Coliseum
200 times. This created an island with
area of 12.98 square kilometre, which
added 1% to the land area of Hong
Kong.
2. Foundation of the Airport - Being in
the man made island, the airport
terminal was to be nailed to the
foundation to save it from ocean tides
which could blow off the terminal
from its foundation. The terminal was
nailed to the bed rock by concrete
piers/piles. Each pile weighed 25 tons.
Mechanism - It consisted of repeating
lattice of steel trusses. 136 such
lattices were produced each of 140
tons. Robotic operator crane, operated
by remote control was used to
assemble these steel lattices.
3. Body of the Airport - Hong Kong was
subjected to average 8 typhoons each
summer and these typhoons are said to
have one of the most destructive forces
on earth, consisting of 200 miles/hr,
composed of wind and water. Airport
would have to withstand typhoons.
Mechanism - Hence, the glass within
the airport was designed to break
under high wind speeds which would
relieve pressure on the building
allowing it to remain standing.
4. Connectivity to the city - As the
airport was constructed outside the
city, so to connect airport with the
main city, following modes were
adopted:
i) Underwater Tunnels - Mammoth
pre-cast concrete steel structures,
weighing 35000 tons (equaling weight
of an ocean liner) were laid 50 ft
under water up to 1 mile for 6 lanes.
Mechanism - To prevent water from
entering them while being laid, they
were capped with watertight seals,
then put head to tail. The seals were
then removed carefully by hydraulic
jacks and the joint between each was
made air tight.
ii) Suspension Bridges - In another
area, where tunnel seemed infeasible
due to 3 mile width of water and
heavy traffic on the route. So bridges
were proposed. Longest bridges were to
be long enough to span the islands and
high enough to allow most gigantic
ships below it. To minimise the public
sufferings during construction, work
was done at night.
Mechanism - Detailed scaled model
results showed that the bridge would
become dangerously unstable during
high winds. But the bridges could not
be shortened, so were to be made
heavier, to stiffen them. 1000 tons pre-
fabricated deck stations were to be
installed in the span. The strength and
support to the bridge towers was
provided by 3 feet diameter cable
weighing up to 15000 tons. But all this
could not be assembled on ground and
then lifted in air. So they assembled
the bridge in midair by “double decker
mechanism” and “lifting each deck
section by the cables up to 200 ft to
install them at the required level”.

China central Television Headquarters.

Let's compare KBC :-)

Sagrada Familia( The unfinished architectural marvel!

The Church of Hallgrimur (Reykjavik,Iceland)

Am not sure if this real or visualized

Habitat 67 (Montreal,Canada)

2.The Crooked House ( Sopot,Poland)

Who can set this out

Tuesday 24 March 2015

The Vinci Tower (Dubai,UAE)(proposed)

PAVEMENT: FLEXIBLE VS. RIGID

.

Provisions of Rigid, Semi Rigid and Flexible
Pavements as Rural Roads
In near future, the cost of bitumen will go on
increasing. So, various alternates to construct
the roads are to be explored. Though concrete
roads are one of the good alternates, but still
their use is limited. This paper discusses the
merits and demerits of all types of pavements
construction and proposes their optimum use.

Introduction

Development of a country depends on the
connectivity of various places with adequate
road network. Roads are the major channel of
transportation for carrying goods and
passengers. They play a significant role in
improving the socio-economic standards of a
region. Roads constitute the most important
mode of communication in areas where
railways have not developed much and form
the basic infra structure for the development
and economic growth of the country. The
benefits from the investment in road sector
are indirect, long-term and not immediately
visible. Roads are important assets for any
nation. However, merely creating these assets
is not enough, it has to be planned carefully
and a pavement which is not designed
properly deteriorates fast. India is a large
country having huge resource of materials. If
these local materials are used properly, the
cost of construction can be reduced. There are
various type of pavements which differ in their
suitability in different environments. Each type
of pavement has it’s own merits and demerits.
Despite a large number of seminars and
conference, still in India, 98% roads are having
flexible pavements. A lot of research has been
made on use of Waste materials but the role
of these materials is still limited. So there is
need to take a holistic approach and mark the
areas where these are most suitable
.
Types of Pavements

There are various type of pavements
depending upon the materials used. A briefs
description of all types is given here.
Flexible Pavements
Bitumen has been widely used in the
construction of flexible pavements for a long
time. This is the most convenient and simple
type of construction. The cost of construction
of single lane bituminous pavement varies
from 2000000 to 3000000 ksh per km in plain areas. In
some applications, however, the performance
of conventional bitumen may not be
considered satisfactory because of the
following reasons:
In summer season, due to high temperature,
the bitumen becomes soft resulting in
bleeding, rutting and segregation finally
leading to failure of pavement.
In cold season, due to low temperature, the
bitumen becomes brittle resulting in cracking,
raveling and unevenness which makes the
pavement unsuitable for use.
In rainy season, water enters the pavement
resulting into pot holes and sometimes total
removal of bituminous layer.
In hilly areas, due to sub zero temperature, the
freeze thaw and heave cycle takes place. Due
to freezing and melting of ice in bituminous
voids, volume expansion and contraction
occur. This leads to pavements failure.
The cost of bitumen has been rising
continuously. In near future, there will be
scarcity of bitumen and it will be impossible
to procure bitumen at very high costs.
Recently, a large number investigations have
demonstrated that bitumen properties (eg.
viscoelsticity and temperature susceptibility)
can be improved using an additive or a
chemical reaction modification.
The use of polymer modified bitumen’s (PMBs)
to achieve better asphalt pavement
performance has been observed for a long
time. The improved functional properties
include permanent deformation, fatigue and
low temperature cracking. The properties of
PMVs are dependent on the polymer
characteristics and content and bitumen
nature, as well as the blending process.
Despite the large number of polymeric
products, there are relatively few types which
are suitable for bitumen modification (2). The
polymers that are used for bitumen
modification can be divided onto two broad
categories, namely plastomers and elastomers.
Elastomers have a characteristically high
elastic response and, therefore, resist
permanent deformation by stretching and
recovering their initial shape. Plastomers from
a tough, rigid, three dimensional network to
resist deformation. The thermoplastic rubber,
styrene butadiene-styrene (SBS), is an
example of an elastomer and the
thermoplastic polymer, ethylene vinyl acetate
(EVA), is an example of a plastomer. One of
the principal plastomers used in pavement
applications is the semi-crystalline copolymer,
ethylene vinyl acetate (EVA). EVA polymers
have been use in road construction for more
than 20 years in order to improve both the
workability of the asphalt during construction
and its deformation resistance in service.

Semi Rigid Pavements
The pavements constructed using the waste
materials, which are more strong the
traditional aggregates may be treated as
Semi-Rigid Pavement. A lot of research work
has been done in this direction. But the work
in terms of real construction is not visible.
Prior to
1991, a major portion of GBFS was being used
by the cement manufacturing industries
located in the nearby areas but its utilization
in this industry has been decreasing gradually.
This material has, therefore, been piling up
gradually due to increased production as a
waste in the plant area an posing serious
problem for its disposal

In a project example, Conventional moorum,
gravel, sand or lime/cement stabilised local
soil were used in subbase layer of a road
pavement. In order to compare the structural
performance of these materials with the steel
industry wastes, a small test track was
constructed . The selection of
different test sections was made on the basis
of laboratory test results as discussed in the
previous sections. The details of the test
sections are as follow:
In order to structurally evaluate the different
specifications/test sections, plate load tests
were conducted on each section using a 30cm
diameter plate. The load deflection values
were recorded by applying incremental load.
Plate load test was also carried out on
subgrade soil. Since with an ordinary truck,
only limited magnitude of reaction can be
obtained, a heavy 35 tonnes dumper was used
for carrying out place load test. Based on
Burmister’s two layer theory, the modulus of
elasticity for different specifications were
worked out and are given in Table-2. The
ratings based on load carrying capacity of
different sections are also indicated in the
same table.
.
Rigid Pavements
Rigid pavements, though costly in initial
investment, are cheap in long run because of
low maintenance costs. There are various
merits in the use of Rigid pavements (Concrete
pavements) are summarized below:
Bitumen is derived from petroleum crude,
which is in short supply globally and the price
of which has been rising steeply. India imports
nearly 70% of the petroleum crude. The
demand for bitumen in the coming years is
likely to grow steeply, far outstripping the
availability. Hence it will be in India’s interest
to explore alternative binders. Cement is
available in sufficient quantity in Kenya, and its
availability in the future is also assured. Thus
cement concrete roads should be the obvious
choice in future road programmes.
Besides the easy available of cement, concrete
roads have a long life and are practically
maintenance-free.
Another major advantage of concrete roads is
the savings in fuel by commercial vehicles to
an extent of 14-20%. The fuel savings
themselves can support a large programme of
concreting.
Cement concrete roads save a substantial
quantity of stone aggregates and this factor
must be considered when a choice pavements
is made,
Concrete roads can withstand extreme weather
conditions – wide ranging temperatures, heavy
rainfall and water logging.
Though cement concrete roads may cost
slightly more than a flexible pavement
initially, they are economical when whole-life-
costing is considered.
Reduction in the cost of concrete pavements
can be brought about by developing semi-self-
compact

Friday 13 March 2015

DAM ENGINEERING RESPONSIBILITY

An Engineer's responsibility is to safety.
They must act with integrity giving due
consideration to the purpose of the project
and the ultimate effects of the project on
fellow human beings.
At the same time the Engineers are
responsible to the community for the cost of
the structure. There is always a limit to the
finance, so any cut in cost must not
sacrifice safety.
The Engineers also carries a legal
responsibility, and are responsible at all
times for both what they do and what they
say.
Consequences of Failure
Failure happens with fearful rapidity and
usually without little warning, with the
potential to cause a national catastrophe.
When the Oros Dam failed in Brazil in
March 1960, between 30 and 50 people were
lost and 100 000 people were evacuated,
some 730 million cubic metres of water
were released in 34 hours with a peak flow
of 9600 cubic metres per second.

Statistics - Classification of Risk according
to Gruner
45% Hydraulic Conditions
30% Type of Structure amd Construction
7% Geology
6% Environment
6% Consequences

Tuesday 3 March 2015

Jobs

Civil Engineering Job Qualifications

Qualified with a Degree in Civil Engineering
Good command of spoken English to
represent the company in Government
Meetings as well as on site .
Has computer knowledge.
Can prepare project certificate for contract
payments
Hold site meeting on behalf of the company
Should qualify for a position as a site
agent as well for our contract
Can prepare claims
Should be able to account for a full project
on cash flow
Can take charge of a large labor force on
site
Will report directly to the Managing
Director on daily basis on progress of site
Should be sincere and hardworking.
Should be a registered Civil Engineer
Interested candidates are invited to send their
Curriculum clearly indicating the position they
are applying for to recruitment@amsol.co.ke
Please note that only short listed candidates
will be contacted

JOBS

With headquarters in Nairobi, Kenya, AFEX
provides international standard service
delivery, combined with 30 years of regional
operational experience.
The AFEX Team is dedicated to ensuring
clients have peace of mind that their projects
will run on schedule and to budget, with their
personnel being cared for to a high
international standard.
AFEX wishes to recruit a competent,
innovative and self-driven person to fill the
following position: 

Building Services

EngineerResponsible for the
design, installation, operation and monitoring
of the mechanical, electrical, plumbing and
public health systems required for the safe,
comfortable and environmentally friendly
operation of modern buildings.
Key Responsibilities:
Assessing and surveying sites prior
to construction.
Designing and specifying of energy
distribution, water pipes and
ventilation systems.
Identifying the materials and
equipment to be used in the various
systems.
Drawing up of Design drawings,
generation of specifications and bill
of quantities.
Drawing up mechanical services
design drawings & Construction
working drawings, writing briefs and
reporting on progress.
Monitoring the installation of
services and managing their
maintenance once the structure is
completed.
Making sure that all building
services meet health and safety
requirements and environmental
legislation.
Liaising with plumbers,
electricians, surveyors, architectural
technologists and other construction
professionals.
Promoting energy efficiency and
other sustainability issues.
Managing teams of people and
working closely with them to get the
work completed on time and to a
high standard.
Design and sizing of pumps, water
filtration equipment and WWTP.
Research and development of
efficient & economical building
services.
To understand the AFEX
requirement for QHSE in the
workplace including employee and
team responsibilities, to ensure
continuous adherence to QHSE
policies, procedures and work
instructions and to proactively
promote a quality, health and safety
approach in all areas of your work.

Minimum Qualifications

Degree in Engineering (Building
services or Equivalent)
Masters in Engineering as an
added advantage.
5 years experience in Building and
Services engineering
Knowledge in Autocad

Application

Applicants meeting the requirements should
send their application and detailed Curriculum
Vitae giving names and contact details of
three referees by Friday, 6th March 2015 to
careers@afexgroup.com

Structural Failure

All efforts are essential to prevent structural
failure as it involves dangers to human life
and property. There are numerous causes for a
structural failure, and there is a requirement
for a proper analysis of all the factors before
construction.

Reasons Structures Fail
Defective construction that causes failure may
be due to numerous reasons that may not be
easy to predict before or during the
construction. The major causes of structural
failure are defective designs that have not
determined the actual loading conditions on
the structural elements. Inferior construction
materials may also be the cause since the
loads are calculated for materials of specific
characteristics. Structure may fail even if the
design is satisfactory, but the materials are
not able to withstand the loads. Employment
of unskilled labor on construction work is
another reason for structural failures.
Therefore, it is important that the owners,
designers, and builders are fully conscious of
the reasons of failure, and undertake all
preventive measures.

Design Deliberations
Construction imperfection in design and
manufacturing can be extremely expensive to
settle. Architectural design and construction
defects cause a structure to be improper for its
proposed intent. Correct structural design is
significant for all buildings, but exceptionally
essential for tall buildings. Even a slight
probability of failure is not acceptable since
the results can be disastrous for human life
and property. Therefore, civil engineers are
required to be exceptionally careful and
methodical in ensuring an appropriate
building design that can sustain the applied
loads. All failure modes need to be examined
by using modern software on the subject.
However, a designer and a builder cannot be
wholly confident about the design, and
therefore an appropriate factor of safety is
incorporated on the design calculations.

Defects Due to Inferior Workmanship

Defects due to inferior workmanship can lead
to structural damage and failure. Poor
workmanship is often the origin of
construction defects. Even superior quality
materials, if used imperfectly, may not
successfully serve the planned function, or be
as durable as designed. Poor workmanship is
the actual cause of most construction defects.
General defects due to poor workmanship are
leaking roofs, cracked floor tiles, shedding
paint, and other numerous problems. Proper
procedures have been created for almost every
construction operation, and only
implementation is required. A superior quality
paint that is applied to an unclean surface is
likely to fail, not because the material was
substandard, but because it was used with a
poor quality of work.

Foundation Failure

Many building foundations are not properly
designed and constructed for the existing site
soil conditions. Since suitable land is often
not available,
buildings are constructed
on soil that has
inadequate bearing
capacity to support the
weight of the structure.
Furthermore, the near
surface soils may consist
of expansive clays that
shrink or enlarge as the
moisture content is
changed. Movement of foundation may occur
if the clay moistening and drying is not
uniform. Vegetation, inadequate drainage,
plumbing leakage, and evaporation, may
cause soil variation. The top soil layers
provide the bearing capacity to hold the
structure, and ensure stability of the
foundation. If the bearing soil is inadequately
compacted preceding construction, the
foundation may be affected by settlement.

Monday 2 March 2015

Is excess cover good in insitu RC structures?

Many times, during my site inspections, I
have found fault with the Contractors for
providing an inadequate cover for the
reinforcements in R.C structures.
Obviously inadequate cover for the R.F
has to be rectified immediately as less
cover causes the larger crack widths in
concrete and thereby it exposes the
reinforcement to surrounding
environment to get corroded. This is an
important factor to consider in which
bridge structures as it withstand severe
environmental conditions.
Furthermore, an inadequate cover leads
to unsatisfactory fire resistant as well as
the under developed bond strengths
between concrete and R.F also. Hence
there should not be any argument
whether inadequate cover is acceptable
or not. The clear and loud answer is
NO!!!!!

Then what about the other side of the
story? In other words, is provision of an
extra cover than the specified limits
acceptable? Oki doki…take a little time
and come up with an answer………………..
Many distinguished concrete
specifications are very clear on this
matter. The tolerance for the concrete
cover is between +10 mm to -10 mm.
However some inexperienced contractors,
especially small scale subcontractors, do
posses a misconception that increased
concrete cover is acceptable and allowed
to go unnoticed. This is wrong…….
What is the underlying theory behind the
upper tolerance limit of the concrete
cover? The upper limit of the concrete
cover governs by its effect on Crack
widths. Generally the Crack width of the
concrete is governed by three factors
namely
1.) Tensile strain of the point
2.) Distance to the R.F bar from the
concerned point &
3.) Depth of the
tensile zone

In this case, the second factor is
significant and it governs the upper limit
of the concrete cover.  The increased
concrete cover leads to longer distances
of R.F bar from the cracking point.
Hence with an increased concrete cover,
the crack width also becomes larger.
So cover for concrete should be in its
specific limits whether it is plus or
minus…keep checking for that….
Oki guys…that’s it for today…Looking
forward to see your comments on this
topic…. Laters

What is Redistribution of Moments

The concept of ‘Redistribution of
Moments’ which is found in structural
design is often not well understood,
specifically among undergrads.
Furthermore it is mostly confused with
another widely used concept of ‘Moment
Distribution’ which is an essentially a
method used to find the BM & SF in
structurally indeterminate Beams &
Frames.
The Redistribution of Moment is
subjected only to moments which derived
only by elastic analysis methods.
Moment Redistribution is meant to be
that transferring of derived moment from
one place to another while not altering
the total height of the bending moment
diagram. However it meant to be reduce
the BM of one point and in practically
that point become plastic and yield
which meant there will be a rotation.
Let me clarify this by an example
Let we assume that we got a following
Bending Moment envelop from an elastic
analyst of the structural element.

If we do the RF design for this BMD , we
may provide the adequate RF for
hogging BM of 300kNm and sagging BM
of 280 kNm. In that case we neglect that
the ability of the element to withstand
the structural effects as an one unit AND
also neglect that this envelop was
derived by several load cases. Note that
the height of the BM is 580
Let assume that this BM envelop was
derived .

The  height of the each BM diagrams are
400 & 480 respectively.
So we do not want need necessarily  to
design the BM height of 580 that gives
by the envelop.
Instead we reduce the maximum BM by
some percentage ,let syt 70% and
redefined the BM envelop as follows




The total BM height is 475 and it is
nearly equal to critical elastic BM height
of 480.
That is Redistribution of Moments simply
explained.